실제 General ITP를 바탕으로, 이루어져야 하는 검사에 대해 알아보자.

참고한 ITP는 Column / Drum / Pressure Vessels용이다.

(General ITP이므로 실제 Vendor에서 이루어지는 검사와 약간의 차이가 있을 수 있으며,

Project마다 다른 General ITP를 사용하므로 하기 내용은 참고용임을 밝힌다.)

General ITP에 포함된 내용은 아래와 같다.

 

  1. Pre-Inspection Meeting

    Material 관련

  2. Material Certificate (including supplementary mechanical properties)
  3. Identification of Materials
  4. Receiving Inspection (Visual/Dimension & Test Report) for Pressure Parts,
    Flanges, Fittings, Gaskets, Dished Head)
  5. Transfer of Material Marking (Material, Heat No., etc.)
  6. Sub-Orders

    Procedure/Qualifications 관련

  7. Welders / Operators Qualifications – As per ASME Sec IX
  8. Welding Procedure Specification(WPS) + Repair Procedure – As per ASME Sec IX
  9. Welding Procedure Qualification Record(PQR) – As per ASME Sec IX
  10. Inspection Test Plan(ITP)
  11. NDT Procedure / PWHT Procedure
  12. Qualification of personal – Shall be qualified by ASNT or equivalent

    Non-Destructive Testing(NDT or NDE) 관련

  13. Liquid Penetrant / Magnetic Particle Examination
  14. Ultrasonic Examination
  15. Radiographic Examinations
  16. Ferrite / Hardness Checks
  17. Disbonding test(For Clad) – For Claded Items
  18. PMI Test – For Alloy items

    Destructive Testing 관련

  19. Production Test Coupons

    Fabrication 관련

  20. Dimensional / Visual check for Gauge Plate & Jig Plate - Workmanship
  21. Welding Consumable Control – As per approved WPS/PQR
  22. Bevel Preparation / Fit up
  23. Back Gouging before Welding Reverse Side
  24. Welding Parameters / Operation & Repairs – As per approved WPS/PQR
  25. Forming – Workmanship
  26. Dimensional / Visual Check – Workmanship, Components & Dimension
  27. Leak Test for Pad Plate
  28. PWHT (Location Thermocouples, Review of Records)
  29. Hydrostatic or Pneumatic Test (as applicable)
  30. Tightness Test (as applicable)
  31. Trays and Packing

    Painting Inspection 관련

  32. Surface Preparation / Painting

    Preparation for Shipment 관련

  33. Drying / Preservation - Cleanliness
  34. Flange Face Check – with Photo
  35. Packing / Marking – Components markings and taggings
  36. Confirmation of Completion for all required Test and Inspection – Inspection Release Certificate(IRC)

    Final Inspection 관련

  37. Inspection Record Book(IRB)

 